Caretaker's
Report………..April, 2010
Dredging H-6 Cove
Completion of the removal of
the sand pile at H-6 should be completed 4/20 by the Town of Hebron Highway
Dept.
Security
I have not been provided
with a security schedule or a starting time for this year as yet. Gate opening
and closing of the beach parking lots will start on Memorial Day weekend unless
I am told otherwise. The sign for the times will be put up before this.
Barley Straw
Thank you to the volunteers
who stuffed bags and to Scott Forgue for his assistance. I am now trying to
locate any stray bales and only have two onion bags left which were given back
to me. I attempted to place some of the bags in the water on 4/20 but with the
wind and without someone to help, I was not able to get far. I have asked Larry
Zimmerman and Warren Smith and they have thankfully offered to help. I will
begin again on Thursday, 4/22, or Friday, weather permitting. Since I cannot
locate any more onion bags, I will request approval to order more. Algae is
forming now at the H-6 Cove location. I may need to put some straw there.
Docks
I have received approval to
use Warren Smith to help me install the docks at Main Beach and Lollipop. We
will do this sometime next week as I need to work on the barley straw insertion
first.
Lake Maintenance
Personal, car, and one boat
pass were sent with the Newsletter recently to all residents per instructions
from the Board of Directors. I have not been informed of a schedule of dates to
pick up additional passes. July 4th was the only date indicated in the
newsletter, but pick up times are still unknown. If you wish additional boat
passes, please use the form in the newsletter and I will send them out to
residents until a schedule can be decided upon by the BOD and the residents
notified. Jo and I have signed our Boat Inspection Contracts and will mail to
Dave O’Brien. I have put up a temp. sign at the boat launch site with the names
of last year's inspectors. When a permanent list is known, it should be put up
and noted on our web site.
Approval or answers are
needed by the Board for the following tasks/questions….tasks
to be completed between this meeting and the next meeting in May:
-
Will the minimum of 6/7 hours still be in
effect for the spring/summer period? When my hours were reduced in November
it was stated that they would be reviewed again in April for the summer
season.
-
The dam grass cutting, tree/bush removal
(required by the DEP) and the trimming of Lollipop walkway, which I did last
year, will you be contracting these tasks out this year?
-
I need to do the spring tune up on the
tractor and other equipment for use this year. (Please note that even if you
are contracting out the brush removal and trimming I need the tractor to
groom the beaches and ROW’s unless this is being contracted out also).
-
I would like approval to purchase sand for
Main Beach this year. It was not done for the last 2 years and needs to the
redone.
-
As stated above, I need approval to order
more onion bags (25/$85.00) .
-
A new cable is need for the parking lot gate
at Main Beach. ($20.00) Approval to purchase?
Along with the several tasks
lists you have already requested and have, I am attaching a listing of the tasks
needed to be done from my inspection of the ALD District Property last week.
If you wish me to complete any of the tasks listed here, please let me know.
Please note
that I have started a clean up of Berglund Green
per Ray DeCormier. I was instructed by Dave O’Brien to bring this before the
Board first, but Mr. DeCormier indicated that if I did not wish to do the task
now, he would hire someone else.
Spafford ROW
Rules signs need replacement
(unreadable)
2 abandoned boat racks need
to be removed (broken & rotted)
Back half needs to be
trimmed & brush removed…..Trash removal
Ryan Terrace ROW
Replace Rules sign with new
Rake some stones back in
place (moved by weather)
1 to 1½ yards sand at beach
area (now 4-6 inch trench due to heavy rains recently)
Minor leaf & branch removal
Clean drains (at bottom)
Lollipop Beach
Will contact ALA….ashes &
nails need to be removed from beach area from New Years’ Eve bonfire.
Leaf & branch
removal…raking….trash removal
Trim parking lot bushes
2nd coat of paint
needed on old sign (1st done last year)
2 coats of paint needed on
new sign
Finish installing bulletin
board
Handicapped sign has been
removed….need to replace
Repaint blue on log to
indicate parking spots for handicapped
Put up hours sign for gate
opening/closing & no dogs sign (needs to be done before Memorial Day)
1 to 11/2 yards sand to fill
around wood terrace system
Lollipop walkway need to be
trimmed before summer
Rules sign need to be
installed
Cove Road ROW
Dead tree on both sides to
be cut and removed
Erosion at Deepwood, near
stream….need to contact Lebanon to rerpair
Two large boat trailers (for
cats) …should be removed…not allowed on ROW
Rules sign to be replaced
Minor leaf & branch removal
Abandon raft need to be
removed from beach area
Six old plastic barrels
(loose) need to be removed
Meadow Brook ROW
Replace rules sign
Untagged boats….. need to
contact owner or be removed
Boat rack needs repair
Lorraine Long, thank you
for your efforts to keep this ROW clean and tidy!
Oakland ROW
Bushes need trimming
(briers) residents have raked and removed branches already THANK YOU!
Rules sign needed
1 to 2 yards of sand for
beach area…need to compress to help prevent erosion
Three boats need to be
removed…..in wring location
Float has been
abandon…..needs to be removed
Francis ROW
Leaf & branch removal
Rake smooth trap rock put on
boat launch area during dredging operation
Replace rules signs
Elsmere ROW
Rules replaced
Boat rack needs to be dug up
& straightened (tilted) Set of 2x4 lumber needs to be replaced (originals gone)
Leaves & branches removed
Check swales and they are ok
Main Beach
Cable needs to be replaced
Remove rest of vines from
cable & clean up area below
Trash clean up
Bushes will need trimming
this summer
New rules sign
Sand needed for beach
Groom beach for summer use
2nd coat of paint
on old sign
2 coats of paint on newer
sign
Entrance to parking lot
breaking off….needs repair
Berglund Green
I am now in the process of
removing branches and trash in prep. for lawn cutting
As I am not able to attend
the April Board meeting, I will need someone to confirm to me my tasks, if any,
for the month. Also I will need the Board to decide on one person I can take my
instructions from so I do not keep getting into a position where I get
conflicting instructions.
Carl Wool, Caretaker |